Backfilling gravel pit - development of a residential and commercial location
At approx. 28 ha site of a former gravil pit a new quarter with a mixture of residential, commercial space and public green and compensation areas will be developed. As the technical project manager omniCon is responsible for the preparation of the backfill operation and its supervision as well as for waste and compensatory concerns. Furthermore we advise the client in all aspects of property conditioning and infrastructure and location development.
Projectdata
Our performance | Technical project management for backfill operation, supervision and waste and compensatory concerns |
Client | CA Immo Deutschland GmbH |
Location | North of the city center and railway station Feldkirchen |
Gross floor area | ca. 280.000 m² |
Construction time | 2009 – 2022 |